Skip to main content
University of Virginia homepage

Office of the University Building Official

Academic Non-Capital

Please submit TCUO paperwork 48 hours ahead of intended occupancy.

*Many of these forms may be unnecessary for minor renovations, elevator upgrades, etc. If a particular form does not apply to your particular project, it will not be required.

All HECO forms are available on UVA Facilities Management's site.

Item Description TCUO CUO Comments
Application for Certificate of Use and Occupancy HECO 13.3 HECO 13.3 For TCUO, click "CERTIFICATE" for option
Certificate of Completion by A/E HECO 13.1a HECO 13.1
Certificate of Completion by Contractor HECO 13.2a HECO 13.2
Final Report of Structural and Special Inspections
(include copy of HECO 6a and 6b for reference)
HECO 13.1b HECO 13.1b
Checklist for Occupancy HECO 13.3b HECO 13.3b For TCUO, click "BENEFICIAL" for option
Copies of Approved Code Modifications N/A Required For final documentation only
Copies of OUBO TCUO/Final Inspection Reports Appreciated when provided Appreciated when provided For TCUO, report may have minor deficiencies if inspector states he/she has no objections to occupancy.
Elevator Inspection Report Required Required For TCUO, report may have minor deficiencies if inspector states he/she has no objections to use.
Approved Testing & Balancing Report Required Required For TCUO, report may have minor deficiencies if Engineer of Record states building is safe for occupancy.
Potable Water Report Required ~ No deficiencies are permitted for TCUO
Verification that FM Asset Turnover Form has been submitted to FM Preventive Maintenance Manager at fm-preventive-maint@virginia.edu w/in 30 days of TCUO Required
Verification that Sprinkler Inventory Form submitted to FireProtection@virginia.edu w/in 30 days of TCUO Required
Verification that Roofing Certificate has been submitted to Facilities Management Roofing Coordinator w/in 30 days of TCUO Required